SAFENET ID:
20250703-0001
Event Start Date:
07/02/2025 1200
Event Stop Date:
07/03/2025 1600 
Incident Name:
Radio Clone Issue
Fire Number:
 
State:
Oregon
Jurisdiction:
USFS
Local Unit:
Umpqua National Forest
Incident Type:
Wildland
Incident Activity:
Line
Stage of Incident:
Initial Attack
Position Title:
Center Manager, Roseburg Dispatch Center  
Task:
 
Management Level:
N/A
Resources Involved:
Crews, Engines, Overhead 
Contributing Factors
Contributing Factors:
Equipment
Human Factors:
Situational Awareness  
Other Factors:
 
Narrative
Describe in detail what happened including the concern or potential issue, the environment (weather, terrain, fire behavior, etc), and the resulting health issue.
Radio communication plan was agreed upon and finalized. The radio tech cloned all of the radios for the forest. During our lightning event and initial attack we had noticed we were not hearing everyone on the radio. The field also realized they were not able to reach us on certain repeaters. At first we thought it was a network error due to having many network issues and the radios going in and out. The crew actually figured out it was a radio clone issue. More than 20 mistakes were cloned into all the radios on the forest.
Some of the issues found; Transmit code guard was wrong, the receive frequency and the code guard wrong on one of the main repeaters, incident tac wrong and this is consistent with about 20 plus channels and effected all groups in the communication plan.
File that is attached was the first round of mistakes found. Then fire personal looked at all the frequencies and found others.
Immediate Action Taken
Reporting Individual : please describe actions you took to correct or mitigate the unsafe/unhealthful event.
The radio tech was contacted. It was made clear what the problem was by the fire personal. A meeting was set up to go over all the issues the next morning. Once the issues were identified a quick clone was done to get one group correct and the others are planned to get fixed over the weekend. Once all the mistakes are corrected another forest wide clone will be completed. The radio tech will work through the weekend to get this done and re cloned before our next lightning event this up coming week.